Reliance Industries will invest another Rs 15,000 crore to build nearly 100 compressed biogas (CBG) plants across India by 2030, according to an announcement by Bio Energy Business CFO Vikas Rathi. The commitment takes the company’s ambitions in an emerging sector to a new level.
Reliance already runs 45 plants across 10 states, producing around 350 tonnes of biogas daily. Its FY26 annual report says the company is targeting more than 500 CBG plants by 2030 and accounts for over 30% of India’s CBG production, supplying green fuel to more than 40,000 vehicles daily.
The Andhra Pradesh connection
The expansion has a direct link to Andhra Pradesh. Reliance earlier committed Rs 65,000 crore to build 500 plants in the state. Anant Ambani, who heads Reliance’s energy operations, later announced a Rs 1 lakh crore investment there.
Building plants before the market matures
India’s CBG industry is far from mature. Government data showed 1,929 CBG plants had been registered by August 2026, but only 217 had been commissioned and 357 were under construction. Reliance is building capacity ahead of demand, which could help it secure feedstock, lock in relationships with farmers and customers, and build cost advantages in technology procurement, plant operations and logistics.
Feedstock is the hard part. Plants need a continuous supply of agricultural residue or other organic waste, and collection is expensive because the material is scattered across villages and its availability changes with the seasons. The company has also said its existing plants are operating below capacity.
Building plants is only one part of the challenge. Ensuring that they run efficiently and generate commercially viable output is the bigger test.
What the GOBARdhan scheme changes
The SATAT initiative, launched by the Ministry of Petroleum and Natural Gas in October 2018, gave developers long-term offtake agreements with IndianOil, BPCL, HPCL, GAIL and IGL. But announced projects still failed to become operating plants, which showed that assured offtake alone was not enough.
The government approved the GOBARdhan scheme in August 2026 with an outlay of Rs 23,731 crore. It runs from FY27 to FY36 and aims to raise domestic CBG production nearly ten-fold to around 5 million standard cubic metres per day. Eligible greenfield projects can receive capital assistance of up to Rs 2 crore per tonne per day of installed capacity.
City gas distribution companies will have to meet CBG procurement obligations of 3% in FY27, 4% in FY28 and 5% from FY29 onwards in the CNG transport and domestic PNG segments. An administered price of Rs 2,110 per MMBtu is intended to give producers greater revenue visibility.
Why the gas angle matters
India wants natural gas to account for 15% of its energy mix by 2030, up from around 6% currently. That goal runs into the country’s dependence on imported LNG. Iranian strikes on Qatar’s energy infrastructure in March 2026 threatened supplies from a country that accounts for around 41% of India’s LNG imports. India imported 11.2 million tonnes of LNG from Qatar in FY25.
CBG cannot replace imported LNG at the scale India needs. It can, however, supply domestically produced fuel to city gas networks, transport users and smaller industries, using feedstock sourced locally.
Is Reliance’s biogas plan part of its wider energy strategy?
Yes. At Jamnagar, Reliance is developing the 5,000-acre Dhirubhai Ambani Green Energy Giga Complex, built around solar manufacturing, battery storage, fuel cells, green hydrogen and power electronics. The company has set a target of enabling 100 GW of renewable energy by 2030 and achieving net-zero carbon emissions by 2035.
What else does the biogas business produce?
Organic manure is a byproduct of CBG plants. The FY26 annual report says Reliance has already engaged more than 80,000 farmers through its bioenergy operations.
TL;DR
- Reliance will invest another Rs 15,000 crore to build nearly 100 CBG plants across India by 2030.
- The company already runs 45 plants across 10 states, producing around 350 tonnes of biogas daily.
- Reliance’s earlier Rs 65,000 crore commitment covers 500 plants in Andhra Pradesh.
- Only 217 of 1,929 registered CBG plants had been commissioned by August 2026, government data showed.
- The GOBARdhan scheme, with an outlay of Rs 23,731 crore, aims to raise domestic CBG output nearly ten-fold.
- Feedstock supply and plant utilisation remain the industry’s biggest structural challenges.