Bharti Airtel plans to invest about Rs 1,200 crore in three data centres in Assam, the company said in a statement on Wednesday.
Where the money goes
Airtel said about Rs 700 crore will go into the Guwahati data centre, while Rs 500 crore will be spread across projects in Jorhat and Silchar.
The Guwahati facility is the first of the three. Airtel signed agreements with the Assam government for it in March, and construction is already underway.
The Jorhat and Silchar projects come under a fresh memorandum of understanding signed with the Assam government in the presence of Chief Minister Himanta Biswa Sarma.
Capacity and phase one spending
The proposed Jorhat data centre will sit on roughly four acres with a capacity of 10 MW. Its proposed Phase 1 investment is Rs 200 crore.
The Silchar site is larger, at about five acres, with a planned capacity of 15 MW. Phase 1 there is pegged at Rs 255 crore, according to the transcript of the Chief Minister’s remarks.
Timeline
Bharti Enterprises Vice Chairman Rajan Bharti Mittal said land has been made available for all three facilities. He said all three data centres could be in place by 2028.
The Bharti delegation at the signing included Rajan Mittal, Rahul Vatts, Director of Corporate Affairs and Group Chief Regulatory Officer at Bharti Airtel, and members of Airtel’s North East team.
Key Facts
Total planned investment across Assam: about Rs 1,200 crore.Guwahati: about Rs 700 crore, with construction already underway.Jorhat: roughly four acres, 10 MW capacity, Phase 1 at Rs 200 crore.Silchar: roughly five acres, 15 MW capacity, Phase 1 at Rs 255 crore.Target completion for all three: 2028, per Rajan Bharti Mittal.Bharti Airtel plans to invest about Rs 1,200 crore in three data centres in Assam, starting with a data centre in Guwahati.
TL;DR
- Airtel plans Rs 1,200 crore across three Assam data centres.
- Guwahati facility, about Rs 700 crore, is already under construction.
- Jorhat and Silchar projects account for about Rs 500 crore under a fresh MoU.
- Jorhat: roughly four acres, 10 MW capacity, Phase 1 at Rs 200 crore.
- Silchar: roughly five acres, 15 MW capacity, Phase 1 at Rs 255 crore.
- Rajan Bharti Mittal says all three could be operational by 2028.