Calcutta High Court Postpones Great Nicobar Island Project Hearing
The Calcutta High Court’s final hearing on a batch of petitions challenging the Union government’s ₹92,000 crore Great Nicobar Island (GNI) project was deferred on Wednesday, November 25, 2026. The bench, led by Chief Justice Ravindra Vithalrao Ghuge, pushed the proceedings after the Centre sought time to submit an additional affidavit and documents concerning tribal rights.
Legal Battles and Forest Rights Disputes
The petitions allege forest rights violations in diverting 121 square kilometers of forest land for the massive infrastructure project. During the proceedings, Additional Solicitor General Vikramjit Banerjee and Attorney General R. Venkatramani represented the government, arguing that the Forest Rights Act (FRA), 2006, is not implemented in the Andaman and Nicobar Islands because the Protection of Aboriginal Tribes Regulations, 1956, is already operational. Petitioners strongly rebutted this, pointing out that the local islands administration previously issued a certificate claiming FRA rights had been settled, which forms the core of their legal challenge.
The Centre argued that the FRA is not implemented in the A&NI, which the petitioners rebutted.
The Centre also raised preliminary objections regarding the maintainability of certain petitions, suggesting some matters should go to the National Green Tribunal or the Supreme Court instead. Petitioners countered that these specific petitions deal with orders reducing buffer zones for two national parks on the island.
Upcoming Court Timeline
The High Court granted the Centre 10 days to file its affidavits and documents, while giving the petitioners until the December winter break to file their rejoinder. The court scheduled the next hearing for January 13, 2027, to address tribal rights and the FRA, followed by the Attorney General’s submissions on January 22, 2027.
Key Facts
Project Cost: ₹92,000 crore for the Great Nicobar Island (GNI) project.Land Diverted: 121 square kilometers of forest land.Next Hearing Date: January 13, 2027, at the Calcutta High Court.Key Legislation debated: Forest Rights Act, 2006 and Protection of Aboriginal Tribes Regulations, 1956.Why was the Great Nicobar Island project hearing deferred?
The hearing was deferred after the Centre requested additional time to file a new affidavit and documents addressing tribal rights and preliminary maintainability objections.
What is the core legal dispute regarding the Forest Rights Act?
The Centre argues the Forest Rights Act does not apply in the Andaman and Nicobar Islands, while petitioners point to an administration certificate claiming those rights were already settled.
TL;DR
- Calcutta High Court deferred the final hearing on the Great Nicobar Island project to January 13, 2027.
- The Centre sought additional time to file affidavits and documents regarding tribal rights.
- Petitioners challenge the diversion of 121 sq.km. of forest land and alleged Forest Rights Act violations.
- The legal battle involves disputes over whether the Forest Rights Act applies in the Andaman and Nicobar Islands.